High Quality Aluminum Formwork Set, Formwork for Building Project, Aluminum Kickers Supporting System Suppliers in China

Home > Products > Formwork > Aluminum Formwork Set For Building Project

Aluminum Formwork Set For Building Project

  • Aluminum Formwork Set For Building Project
  • Aluminum Formwork Set For Building Project
  • Aluminum Formwork Set For Building Project
  • Aluminum Formwork Set For Building Project

Aluminum Formwork Set For Building Project

    Payment Type: L/C,T/T,D/P
    Terms of Trade: FOB,CIF,EXW
    Min. Order: 500 Square Meter
    Delivery Time: 30 Days
    Packaging: standard packing
    Productivity: 10000 square meters/month
    Brand: Hong Ying
    Transportation: Ocean
    Place of Origin: Huizhou,China
    Supply Ability: 10000 square meters/month
    Certificate: ISO9001:2015,ISO14001:2015
    HS Code: 7610900000
    Port: Shekou,Nansha

Basic Info

Model No.: Formwork

Product Description

Formwork Installation Process:



Aluminum Formwork Installation Disclosure

1-2 days before installation of the first layer of aluminum formwork,the person in charge of aluminum formwork shall organize relevant operators to be familiar with the installation coding diagram of aluminum formwork and conduct division disclosure.

Construction Setting Out

After the concrete pouring is completed and the floor concrete reaches a certain strength,the construction positioning and setting out shall be carried out immediately, and the positioning line of wall column shall have zero error.

Ground Elevation Inspection and Chiseling

The elevation and mark shall be conducted along the positioning line of the wall column. After the straightening is completed, the part higher than the concrete shall be removed with a large crowbar or electric pick to make it slightly lower than the structural elevation.

Welding of Positioning Reinforcement

There shall be no false welding in the welding process,
and the duration of each welding shall be ≤ 5 seconds,
welding space of positioning bar ≤ 1000mm

Lifting Formwork, Node Removal

During the construction and setting out, the formwork shall be lifted and the nodes shall be removed simultaneously. During the folding process, it is not allowed to smash and pry hard, and the finished concrete products shall be protected from damage.

Remove the Aall Column Formwork

After the formwork removal conditions are met or the formwork removal is approved, the wall column formwork shall be removed. Before the removal of the wall column formwork, the diagonal brace, Steel Wire Rope and Other fasteners shall be removed first.

Wall Column Formwork Transfer

After the removal of the wall column and floor slab, the whole body shall be coated with the release agent, which shall be transferred to the corresponding position in sequence according to the formwork installation sequence, the formwork code.

Wall Column Formwork Installation

The wall column slab shall be transferred to the corresponding position,and the wall column formwork shall be installed after the completion of embedded acceptance of Rebar,water and electricity.

Initial Adjustment of Wall Column Formwork

After the wall column formwork is installed, the elevation adjustment and the initial adjustment of verticality of the wall column formwork shall be carried out immediately. Before the initial adjustment, the verticality error shall be calibrated ≤ 3mm.

Remove the Beam Formwork

After the internal wall formworks are all transferred to the installation layer, the beam formworks shall be removed. Before the formworks are removed, it shall be confirmed that the work bench is safe and reliable, and there is no other material around.

Beam Formwork Installation

Before the installation of beam bottom formwork, confirm that the connection of beam bottom formwork is stable, the beam bottom installation is completed and the support is stable before the installation of beam side formwork.

Remove the Floor Formwork

After all the beam formworks are transferred to the installation floor, the floor formworks shall be removed. The bottom cage shall be removed first, then the panel shall be removed, and finally the floor C shall be removed.

Floor Formwork Installation

The beam formwork shall be installed firmly, and the floor formwork shall be installed. Before installation, it shall be confirmed that the bottom cage is supported firmly as required.


aluminum formwork

aluminum formwork installation process

aluminum formwork


Guangdong Yonglong Aluminum Co.,Ltd

  • 1
  • 2
  • 3
  • 4
 

Guangdong Yonglong Aluminum Co., Ltd. is headquartered at No. 10 Lequn Avenue, Leping Town, Sanshui District, Foshan City. The company was founded in 1997. It is a comprehensive large-scale Aluminum Profile enterprise integrating R&D, production and sales of Aluminum Alloy Profiles. The company is leading the management of "Hongying" aluminum brand and "Konuk KLUK" high-end system doors and windows brand. With strong comprehensive strength and high-quality service, Yonglong products sell well all over the country and are exported to Southeast Asia, the Middle East, Europe, South America, North America and many Other countries and regions.


Our company have nearly 1,000 employees, including 150 senior and intermediate engineering and management personnel. It has a senior R&D and design team, introduces advanced production equipment and testing and inspection technology, and builds a complete sales network and after-sales service system. The products are sold throughout the country. And Hong Kong, Macao and Taiwan regions, as well as more than 30 countries in Southeast Asia, Europe, and North America.


Our company has 25 modern aluminum profile production lines and 35 quality inspection equipment (sets), integrating melting and casting, mold, extrusion, mechanical frosting, anodizing, electrophoretic coating, powder spraying, thermal transfer wood grain, heat insulation production lines, Glue injection/striping, deep processing of industrial aluminum, and the introduction of advanced porcelain bathing surface treatment technology. With its superb technology and craftsmanship, it stands in the woods of the aluminum industry and is highly praised by customers. After years of development, the company has passed ISO9001:2015 quality management system certification and international standard product certifications.

Company Info

  • Company Name: Guangdong Yonglong Aluminum Co.,Ltd
  • Representative: Weiwen Chen
  • Product/Service: Aluminum Profiles , Aluminium Extrusion , Aluminum Windows , Aluminium Doors , Aluminium Curtain Walls , Aluminum Formwork
  • Capital (Million US $): 10,000,000RMB
  • Year Established: 1997
  • Total Annual Sales Volume (Million US $): US$50 Million - US$100 Million
  • Export Percentage: 61% - 70%
  • Total Annual Purchase Volume (Million US $): US$5 Million - US$10 Million
  • No. of Production Lines: 25
  • No. of R&D Staff: 11 -20 People
  • No. of QC Staff: 11 -20 People
  • OEM Services Provided: yes
  • Factory Size (Sq.meters): 10,000-30,000 square meters
  • Factory Location: No.10 Lequn Avenue,Leping Town,Sanshui District,Foshan City,Guangdong Province, P.R. China
  • Contact Person: Ms. Susan
  • Tel: 86-757-87392211
Email to this supplier
  • *Subject:
  • To:

  • *Messages:
    Your message must be between 20-8000 characters